This blog focuses on real estate, land use and construction-related topics affecting Virginia and the Washington, D.C. metro area. With topics ranging from contract drafting and negotiation to local and regional land use project updates, the attorneys at Bean, Kinney & Korman provide timely insight and commentary on the issues affecting owners, builders, developers, contractors, subcontractors and other players in the industry. If you are interested in having us cover a specific topic, please let us know.

Contact us

Topics

Archives

Select Month:

Contributors

Posts tagged liquidated damages.

Earlier this year, the Virginia Supreme Court decided Martin Brothers Contractors, Inc. v. Virginia Military Institute, taking the opportunity to revisit its decision in Blake Construction.

The Virginia Military Institute (“VMI”) contracted with Martin Brothers to renovate VMI’s main dining facility. During the project, VMI requested changes resulting in a 270-day delay. VMI agreed that it alone was responsible for the delay. Martin Brothers sought $430,242.56 in delay damages plus the costs of recovery.